News

TransAlta secures access to Alberta’s grid under AI data-centre plan

News

TransAlta secures access to Alberta’s grid under AI data-centre plan

The Calgary utility company’s natural gas project near Edmonton has been granted the last of the highly sought-after power capacity the province reserved for data centres

By Jesse Snyder
TransAlta's Keephills power plant at Wabamun, Alberta, in a 2023 handout image. Photo: TransAlta/Handout
Nov 10, 2025
A A
A Small A Medium A Large
Share

Gift

Share

CALGARY — TransAlta has won the right to tap into Alberta’s electrical grid to run a data centre, securing the last of a highly sought-after pool of power capacity the province has set aside to fuel its AI ambitions.

On Wednesday, the Alberta Electric System Operator (AESO), which operates the province’s power grid, allocated 230 megawatts of capacity to TransAlta’s Keephills project, a natural gas facility located 70 kilometres west of Edmonton. The decision means that TransAlta will be able to use a portion of the province’s available electricity at Keephills to power a data centre, the energy-hungry engines of “compute,” or computing power, that tech companies need to deliver their services.

Talking Points

  • Alberta wants to be a hub for AI data centres, and has set aside 1,200 megawatts of capacity to power them
  • On Wednesday, the province’s grid operator awarded TransAlta 230 megawatts of that highly sought-after allocation

Keephills is the second and final project to win a portion of AESO’s 1,200-megawatt allocation for “large-load” projects. AESO had already allocated the other 970 megawatts to a facility that would draw power from the Greenlight Electricity Centre, a proposed project near Edmonton that, as The Logic previously reported, could power a data centre for Meta. 

Alberta has ambitions to become a hub for AI data centres, with Premier Danielle Smith arguing that such developments could boost the province’s economic growth. However, Alberta currently lacks the electricity to power data centres on that scale. To address this, AESO in June temporarily capped additional “large-load” projects at a total of 1,200 megawatts to ensure that new AI data-centre developments don’t overburden Alberta’s grid. 

Related Articles

A scenic shot of towering wind turbines and high-tension power transmission lines taken in the rolling farm country of southwestern Alberta. The east slope of the Rocky Mountains rises in the background.

Alberta doesn’t have the electricity to power its AI data dreams

By Jesse Snyder
A wide shot of a rows of towering industrial-style buildings on the Utah desert. There are white pickup trucks parked in the foreground.

Meta, Pembina near deal to build massive Alberta AI data centre

By Jesse Snyder

Alberta touts natural gas as a way to power Silicon Valley’s AI

By Jesse Snyder

AESO’s final allocation means that the remaining data-centre proposals will need to build their projects entirely off-grid—without the provincial power grid as backup to their primary power supplies—until utility companies add new generating capacity. 

The province has received a flurry of data-centre proposals totalling 33 projects that would require more than 20,000 megawatts of power. That’s about equal to the current capacity of Alberta’s entire electricity grid, underscoring the immense power demands of the data centres that Meta, Google, Microsoft and other firms hope to build as they compete in the AI race that has consumed the global tech sector. 

TransAlta did not confirm who its data-centre partner is, saying only that it is “working closely with counterparties and progressing towards finalizing a memorandum of understanding” on Keephills.

In a conference call with analysts on Thursday, TransAlta CEO John Kousinioris said the company’s data-centre project “will contribute to powering a new industry in the province.” TransAlta acknowledged its interest in the 230-megawatt AESO allocation in its latest investor presentation, and also said it had rezoned 3,000 acres of land near its Keephills natural gas facility to accommodate a data centre.

The Keephills facility first came online in 1983, and now has 861 megawatts of capacity. The plant was the last of three Canadian facilities that TransAlta converted to natural generation in 2021 as part of its rapid shift away from coal.

If a hyperscaler eventually builds a data centre at the Keephills site, the 230-megawatt allocation would likely only account for a fraction of the power it would need. Consulting firm Bain expects global data-centre demand to be met largely by a relatively limited number of “campuses” with at least 1,000 megawatts of capacity.

Gift the full article

A few days after The Logic reported that Meta was in talks with Calgary companies Pembina Pipeline and Kineticor to build a large-scale data centre, Pembina informed shareholders that its customer, which it did not name, had secured allocation from AESO. The companies involved in the proposal did not confirm The Logic’s reporting.

Pembina and Kineticor plan to build the Greenlight Electricity Centre in 450-megawatt increments, with plans to reach a final capacity of 1,800 megawatts.

#artificial intelligence #data centres #markets #Tech #TransAlta

Sponsored Content

The road to risk-smart regulation

By Deborah Aarts

Why cybersecurity needs to match pace with AI

By Jessica Aftimus Rosa

How to shift your workforce from AI experimentation to adoption

By Jessica Aftimus Rosa
Paid promotional content

Loading...

Thanks for sharing!

You have shared 5 articles this month and reached the maximum amount of shares available.

Close
This account has reached its share limit.

If you would like to purchase a sharing license please contact The Logic support at [email protected].

Close
Want to share this article?

Upgrade to all-access now

Close
Gift the full article!

You have gifted 0 article(s) this month and have 5 remaining.

Copy link and gift
Copy Link
Email to a friend
Send Email
Gift on Social Media

Recipients will be able to read the full text of the article after submitting their email address. They will not have access to other articles or subscriber benefits.

Photo: TransAlta/Handout

Most Popular This Week

News

RBC’s AI chief sounds the alarm over AI agents

By Chaimae Chouiekh
News

Underperforming AI agents at big banks face a very human pressure: Losing their jobs

By Claire Brownell
News

Brookfield’s new CEO flexes the firm’s soft power with its $50B Canadian bet

By Anita Balakrishnan
A shot taken through laboratory equipment of a researcher injecting liquid into a tube. The worker is wearing blue, latex gloves, and is a white lab coat with the VIDO logo on it.
News

Panel decries Canada’s chaotic way of funding world-class science

By David Reevely

In-depth, agenda-setting reporting

Great journalism delivered straight to your inbox.

News

Ottawa is softening its ban on stablecoin yield

By Claire Brownell

Briefing

Rio Tinto gets nearly $165M in additional federal funds for Quebec aluminum

By Anita Balakrishnan   |   Oct 23, 2026 | 3:43 PM ET

U.S. to lift tariffs on some Canadian products crucial to Maine: Collins

By Joanna Smith   |   Oct 23, 2026 | 3:41 PM ET

Carney warns of tech dependence after Starlink disruptions in Ukraine

By Catherine McIntyre   |   Oct 23, 2026 | 2:42 PM ET

Best business newsletter in Canada

Get up to speed in minutes with insights and analysis on the most important stories of the day, every weekday.

Exclusive events

See the bigger picture with reporters and industry experts in subscriber-exclusive events.

Membership in The Logic Council

Membership provides access to our popular Slack channel, participation in subscriber surveys and invitations to exclusive events with our journalists and special guests.

Recent Popular Stories

News

Brookfield’s new CEO flexes the firm’s soft power with its $50B Canadian bet

By Anita Balakrishnan   |   Oct 21, 2026
Commentary

Carmichael: Canada needs tax reform. Carney shouldn’t make it up as he goes along

By Kevin Carmichael   |   Oct 17, 2026
The Big Read

Beacon is building an AI empire by fixing Main Street’s software

By Murad Hemmadi   |   Oct 19, 2026
A man in glasses and a blue knit sweater outdoors on a city street, with brick buildings softly blurred behind him
News

A tech firm born from post-Brexit trade chaos sets its sights on Canada

By Joanna Smith   |   Oct 13, 2026
A shot of a freight truck passing beneath a gantry that bears signs directing traffic through the Port of Belfast.
News

RBC’s AI chief sounds the alarm over AI agents

By Chaimae Chouiekh   |   Oct 22, 2026
News

Anthropic revealed as client for EverWind’s $10B Nova Scotia data centre

By Catherine McIntyre   |   Oct 16, 2026

Canada's most influential executives and policymakers are reading The Logic

  • CPP Investments
  • Sun Life Financial
  • C100
  • Amazon
  • Telus
  • Mastercard
  • bdc
  • Shopify
  • Rogers
  • RBC
  • General Motors
  • MaRS
  • Government of Canada
  • Uber
  • Loblaw Companies Limited
logic-logo

Canada's Business and Tech Newsroom

100% human-crafted journalism

Newsroom

  • News Tips
  • AI Policy
  • Editorial Disclosures
  • Story Pitches

Company

  • About Us
  • Terms of Service
  • Privacy Statement
  • Corporate Information

Contact

  • Contact Us
  • Advertise
  • FAQs
  • Work at The Logic

© 2026 The Logic Inc. All Rights Reserved.

Trusted by leaders

Error

Account creation failed.

Please email us at [email protected].

Create Account

[wppb-register form_name=”cozmo-registration-form-for-modal”]

I do have an account
Login
or

[wppb-login]

I don’t have an account